A manufacturer of automobile engines is designing a new Kanban system for engine #321. The demand for #321 is 75 parts per day, and the container can hold 8 parts at a time. The total processing and waiting time is 3 days. The manager wants a safety factor ( α ) of 2 or 200 percent. How many Kanbans are required in this system?
A) 85
B) 90
C) 100
D) 115
Correct Answer:
Verified
Q4: _is focused on ensuring that operating systems
Q5: Any activity, material, or operation that does
Q6: The equation used to calculate the
Q7: A_produces finished-goods inventory in advance of customer
Q8: In the context of the 5S principles,
Q10: Total productive maintenance (TPM) seeks to reduce
Q11: Which of the following is an example
Q12: In the context of lean tools and
Q13: In the context of the 5S principles,
Q14: _ is one in which employees at
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents