The District Magistrate of a City Has Decided to Reconstruct

Question 6

Multiple Choice

The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the duration of the work, which will cause considerable inconvenience to the people of the city. The project has three parallel paths defined as the following:
Path A-B-C-H will take 16 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 30 days.
In the given scenario, which of the following statements is true?


A) The expected duration of the project is 68 days.
B) Activities B, D, and F have an earliest starting time of 0.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents