The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the duration of the work, which will cause considerable inconvenience to the people of the city. The project has three parallel paths defined as the following:
Path A-B-C-H will take 16 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 30 days.
In the given scenario, which of the following statements is true?
A) The expected duration of the project is 68 days.
B) Activities B, D, and F have an earliest starting time of 0.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
Correct Answer:
Verified
Q1: Which of the following stages of the
Q2: Which of the following is an example
Q3: Project managers do not need technical expertise.
Q4: In the project management life cycle, the_involves
Q5: _refers to reducing the total time to
Q7: The Critical Path Method (CPM) allows us
Q8: The Project Evaluation and Review Technique (PERT)
Q9: Which of the following is an assumption
Q10: In the context of the Critical Path
Q11: A pure project organizational structure eliminates the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents