Solved

Which of the Following Is True of the Critical Path

Question 24

Multiple Choice

Which of the following is true of the Critical Path Method (CPM)


A) It allows us to investigate the effects of uncertainty of activity times on project completion times.
B) It uses the variance in the critical path activities to evaluate the risks associated with project completion times.
C) It assumes that activities are independent of one another, with clearly defined start and finish dates.
D) It accounts for the interruptions that may affect an activity between the start and the finish times.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents