Consider the Spreadsheet for Stone Age Surfboards Provided Below -What Is the Allowable Increase in the Finishing Hours Used
Consider the spreadsheet for Stone Age Surfboards provided below. Use this data to answer the following questions) , using the Standard Solver.
Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone and the Lava models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 8 skilled workers, each of whom works
9.25 hours per day. The finishing department has 5 workers, each of whom works a 6-hour shift per day. Each pair of Graystone surfboards requires 2.5 labor hours in the fabrication department and 2 labor hours in finishing. The Lava model requires 4.2 labor-hours in fabrication and 3.6 labor-hours in finishing. The company operates 6 days a week. It makes a per unit profit of $40 on the Graystone model and $60 on the Lava model. The company anticipates selling at least twice as many Lava models as Graystone models.
-What is the Allowable Increase in the finishing hours used?
A) 32.46
B) 8.33
C) 26.84
D) 16.67
Correct Answer:
Verified
Q6: Consider the spreadsheet for Stone Age
Q7: Use the following information to answer
Q8: Consider the spreadsheet for Stone Age
Q9: Use the following information to answer the
Q10: Consider the spreadsheet for Stone Age
Q12: Use the following information to answer
Q13: Consider the spreadsheet for Stone Age
Q14: Use the following information to answer the
Q15: Which of the following best defines objective
Q16: Use the following information to answer the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents