PERT charts differ from critical path method (CPM) in one important way.PERT charts _____, and the CPM does not.
A) assign one time to finish each task
B) are based on the use of quality principles
C) assign three time estimates for each activity
D) can be used in service organizations; and CPM cannot
E) do not help managers locate possible production delays
Correct Answer:
Verified
Q115: One of the biggest shortcomings of Gantt
Q116: The Japanese inventory system that minimizes inventory
Q117: For which of the following businesses would
Q118: There is a laboratory at the North
Q119: _ is the aspect of production control
Q121: _ combines computerized manufacturing processes with other
Q122: A flexible manufacturing system (FMS) combines all
Q123: Point-of-sale (POS) terminals would NOT be helpful
Q124: A CAD/CAM system:
A)reduces costs
B)improves quality
C)shortens design time
D)controls
Q125: The letters CAD stand for:
A)commercial-art design
B)centralized art
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents