_____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic) .This technique allows managers to anticipate delays and potential problems and schedule accordingly.
A) A Gantt chart
B) Prioritization
C) Bottleneck elimination
D) Value-stream mapping
E) The program and evaluation review technique
Correct Answer:
Verified
Q109: _ management emphasizes the use of quality
Q110: A few years ago, when Coca-Cola introduced
Q111: _ is the streamlining of production by
Q112: The process of creating quality standards and
Q113: Total quality management focuses on:
A)creating buyer/supplier dependence
B)computer-aided
Q115: One of the biggest shortcomings of Gantt
Q116: The Japanese inventory system that minimizes inventory
Q117: For which of the following businesses would
Q118: There is a laboratory at the North
Q119: _ is the aspect of production control
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents