A steel plate weighing 27 kN is hoisted by a cable sling that has a clevis at each end. The pins through the clevises are 22 mm in diameter.
Each half of the cable is at an angle of 35 ° to the vertical. The average
Shear stress in each pin is approximately: (A) 22MPa 22 \mathrm{MPa}
(B) 28MPa 28 \mathrm{MPa}
(C) 40MPa 40 \mathrm{MPa}
(D) 48MPa 48 \mathrm{MPa}

 A steel plate weighing 27 kN is hoisted by a cable sling that has a clevis at each end. The pins through the clevises are 22 mm in diameter. Each half of the cable is at an angle of 35 ° to the vertical. The average Shear stress in each pin is approximately: (A)   22 \mathrm{MPa}   (B)   28 \mathrm{MPa}   (C)   40 \mathrm{MPa}   (D)   48 \mathrm{MPa}

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents