A company wants to generate a forecast for unit demand for year 2012 using exponential smoothing.The actual demand in year 2011 was 120.The forecast demand in year 2011 was 110.Using this data and a smoothing constant alpha of 0.1, which of the following is the resulting year 2012 forecast value?
A) 100
B) 110
C) 111
D) 114
E) 120
Correct Answer:
Verified
Q62: Which two of the following are among
Q63: A company wants to forecast demand using
Q64: The exponential smoothing method requires which of
Q64: If a firm produced a product that
Q65: A company wants to forecast demand using
Q70: Which of the following forecasting methods can
Q71: A company wants to forecast demand using
Q74: In general, which forecasting time frame is
Q87: Given a prior forecast demand value of
Q96: Given a prior forecast demand value of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents