Forward Venture Company, Which Uses a Standard Cost System, Budgeted

Question 70

Multiple Choice

Forward Venture Company, which uses a standard cost system, budgeted $600,000 of fixed overhead when 40,000 machine hours were anticipated.Other data for the period were: Actual units produced: 10,000 Standard production time per unit: 3.9 machine hours Fixed overhead incurred: $620,000 Actual machine hours worked: 42,000 Forward Venture Company's fixed-overhead budget variance is:


A) $10,000 favorable.
B) $15,000 favorable.
C) $15,000 unfavorable.
D) $20,000 favorable.
E) $20,000 unfavorable.