You are analyzing a project and have prepared the following data: Based on the net present value of _____ for this project, you should _____ the project.
A) -$2,021.28; reject
B) -$406.19; reject
C) $7,978.72; accept
D) $9,836.74; accept
E) $12,684.23; accept