Large Homes Inc. is currently in the midst of a big residential construction project. The company's operations manager is looking at estimated completion dates for the various phases of construction. A major problem that he encounters is that the site excavation took three weeks longer than anticipated. The operations manager wants to make up the lost time in the other phases, but those phases are also falling behind because of the use of construction materials and methods the company has never used before. Which of the following tools might have helped the operations manager better manage the project scheduling?
A) Enterprise Resource Planning
B) Critical Path Method
C) Computeraided design
D) Vertical integration
Correct Answer:
Verified
Q108: The _ is a project management tool
Q109: The decision about where to locate a
Q110: A _ usually holds large inventories of
Q111: Given the nature of their products, service
Q112: In the last 50 years there have
Q114: Janice, the manager at a local toy
Q115: Most manufacturing firms are concerned about the
Q116: Companies that hold large amounts of inventory
Q117: Blue Casuals Inc. is a manufacturer of
Q118: Anne Miles owns a small business that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents