Which of the Following Can Cause Delays in Production in an MRP

Question 48

Multiple Choice

Which of the following can cause delays in production in an MRP II system?


A) Processing time variability
B) Part delivery variability
C) Both processing time and part delivery variability
D) Neither processing time nor part delivery variability

Correct Answer: