You have determined that a 75 percent learning curve is appropriate for a task. If the initial timing of the person performing that job was 50 minutes, and if you need the job performed 500 times, how many minutes of work will be required?
A) 25,000 minutes
B) 3,184 minutes
C) 1,895 minutes
D) 1,379 minutes
E) 636.8 minutes
Correct Answer:
Verified