Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs. Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the reduction in makespan for the seven jobs?
A) The schedule with job C split is almost a day longer.
B) The schedule with job C split is almost 2 days shorter.
C) The schedule with job C split is almost 2 days longer.
D) There is no difference between the makespan for the original schedule and that made with job C split into two halves.
Correct Answer:
Verified
Q98: Use the information in the table and
Q99: _ is a priority sequencing rule that
Q100: A workstation has five jobs that just
Q101: Table J.12 The Feast
Janice prepares a medley
Q102: Table J.15
Consider the following problem in which
Q104: Table J.17
A company must take on seven
Q105: Lee Beedo, a hip bachelor in Edmond,
Q106: Table J.17
A company must take on seven
Q107: Table J.17
A company must take on seven
Q108: Table J.14
Gable Bakery has five cake orders
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents