An Item Sells at a Rate of 240 Units Per

Question 82

Essay
An item sells at a rate of 240 units per day. If a plant works one shift per day (480 minutes), what takt time is required for the plant to meet this demand?

An item sells at a rate of 240 units per day. If a plant works one shift per day (480 minutes), what takt time is required for the plant to meet this demand?

Correct Answer:

verifed

Verified

480 minutes per day ...