In a network diagram, an activity:
A) is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
B) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
C) should always be something the company has had experience with.
D) must always have a single, precise estimate for the time duration.
Correct Answer:
Verified
Q1: A pure project organizational structure houses the
Q2: A relationship that determines the sequence for
Q3: Following the project defining and organizing phase,
Q5: The work breakdown structure is a statement
Q6: Project managers should be able to organize
Q7: Projects, and the application of project management,
Q8: A project organization structure where team members
Q9: Scope creep is one of the primary
Q10: A project is an interrelated set of
Q11: _ determines the sequence for undertaking activities.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents