Multiple Choice

Table 7.4
-Using Table 7.4, what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date?
A) one activity
B) two activities
C) three activities
D) four or more activities
Correct Answer:
Verified