Solved

Table 7.3 -Using Table 7.3, If the Project Manager Wants at Least

Question 120

Multiple Choice
Table 7.3
 
-Using Table 7.3, if the project manager wants at least a 98% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager?
A) fewer than or equal to 28 days 
B) greater than 28 days but fewer than or equal to 30 days 
C) greater than 30 days but fewer than or equal to 32 days 
D) greater than 32 days

Table 7.3
Table 7.3    -Using Table 7.3, if the project manager wants at least a 98% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager? A)  fewer than or equal to 28 days B)  greater than 28 days but fewer than or equal to 30 days C)  greater than 30 days but fewer than or equal to 32 days D)  greater than 32 days
-Using Table 7.3, if the project manager wants at least a 98% probability that the project will be completed on or before the due date, what is the shortest project due date that will satisfy the manager?


A) fewer than or equal to 28 days
B) greater than 28 days but fewer than or equal to 30 days
C) greater than 30 days but fewer than or equal to 32 days
D) greater than 32 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents