Solved

If the Sum of the Variances on the Critical Path

Question 128

Multiple Choice
If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?
A) 50 percent
B) 95 percent
C) 100 percent
D) It cannot be determined.

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?


A) 50 percent
B) 95 percent
C) 100 percent
D) It cannot be determined.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents