Available-to-promise (ATP) quantities are only shown in the first period (if the projected on-hand inventory is greater than zero in the first period), and subsequently in periods when the MPS quantity is greater than 0.
Correct Answer:
Verified
Q1: Gross requirements are the total demand derived
Q15: The projected on-hand inventory in the MPS
Q16: _ is a computerized information system developed
Q17: The master production schedule (MPS) is the
Q18: Material requirements planning (MRP) is a computerized
Q19: Under which one of the following circumstances
Q21: Complete the following MPS Record.
Q23: For items manufactured in-house, one component of
Q24: A bill of materials is a record
Q25: Table 11.1
Big Truck Tacos has developed the