If an Assignment Problem Consists of 5 Workers and 4

Question 42

Multiple Choice

If an assignment problem consists of 5 workers and 4 projects:


A) one worker will not get a project assignment.
B) one project will be assigned two workers.
C) the fifth worker will split time among the four projects.
D) one project will not get a worker assigned.
E) The problem cannot be solved by assignment method.

Correct Answer:

verifed

Verified