A Work Cell Is Scheduled to Build 120 Digital Light

Question 272

Essay

A work cell is scheduled to build 120 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theater projection systems. The work cell has 6.5 hours of productive work each day, five days per week. What is takt time for this cell?

Correct Answer:

verifed

Verified

The cell has 6.5 × 5 = 32.5 ho...