An assembly line with 11 tasks is to be balanced. The longest task is 3.2 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 16 minutes. The line will operate for 600 minutes per day.
(a) Determine the minimum and maximum cycle times.
(b) What range of output is theoretically possible for the line?
(c) What is the minimum number of stations needed if the maximum output rate is to be sought?
(d) What cycle time will provide an output rate of 200 units per day?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q307: Assembly line balancing has just been used
Q308: _ is the maximum time that the
Q309: You have been asked to balance a
Q310: Identify the five common layout heuristics used
Q311: A company is trying to balance production
Q313: A firm operates a flow shop building
Q314: Develop a solution for the following line
Q315: Identify the formulas for the following terms
Q316: Hemo-tech, Inc., a biomedical technology and research
Q317: A(n) _ line is a machine-paced product-oriented
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents