A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of B and of C. B is an immediate predecessor of D and of E. C is an immediate predecessor of E. Which of the following statements is TRUE?
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are three paths in this network.
E) There are six paths in this network.
Correct Answer:
Verified
Q42: Activity D on a CPM network has
Q43: Which of the following statements regarding critical
Q44: The fundamental difference between PERT and CPM
Q45: Slack is the amount of time an
Q46: The network analysis method that allows activity
Q48: Identify, in order, the six steps basic
Q49: The difference between AON and AOA networks
Q50: The _ is the computed longest time
Q51: Which of the following statements regarding CPM
Q52: Activity R on a CPM network has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents