Which of the following statements regarding time-cost tradeoffs in CPM networks is FALSE?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
Correct Answer:
Verified
Q112: In project management, crashing an activity must
Q113: Consider the network described in the table
Q114: Describe in words how to calculate a
Q115: Contract requirements state that a project must
Q116: Project management at the Tour de France
Q118: A partially solved PERT problem is detailed
Q119: If an activity whose normal duration is
Q120: Shortening the project's duration by deleting unnecessary
Q121: Pirmin's Bike Shop is behind on a
Q122: Which of the following is NOT a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents