The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
A) schedule
B) cost
C) budget
D) time
E) performance
Correct Answer:
Verified
Q71: Conditions or scope can change during execution,
Q72: A negative CV indicates the project is
Q73: When someone familiar with each task estimates
Q74: The value that tells you how much
Q75: Which of the following is not one
Q77: Taking action in the four steps for
Q78: The project network schedule is derived from
Q79: A negative cost variance combined with a
Q80: The start of a task may be
Q81: What is the difference between a baseline