When a developer decides to break down the project design into sequential phases and begins construction before the last phases of the design are complete, this procedure is more commonly referred to as
A) build-to-suit construction
B) coordination construction
C) design-build construction
D) fast-track construction
Correct Answer:
Verified
Q22: Which of the following types of engineers
Q23: Which of the following types of engineers
Q24: In considering the main components of a
Q25: Which of the following types of engineers
Q26: The construction budget has six main components:
Q27: Which of the following individuals focuses on
Q28: The second stage of the development process
Q29: After construction has been completed, a developer
Q30: Based on your understanding of the relation
Q32: For all but the largest of developers,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents