There are three basic causes for change in projects and their budgets and/or schedules. Which of the following is not one of these?
A) Errors the cost estimator made about how to achieve the tasks identified in the project plan.
B) Inflation causes significant changes to the cost of labor and/or materials.
C) The project team or client learns more about the nature of the scope of the project or the setting in which it is to be used.
D) A new law is passed, a trade association sets a new standard, a governmental regulatory agency adopts a new policy.
Correct Answer:
Verified
Q48: Victor, a project manager, is constructing a
Q49: Sean, a project manager, has to prepare
Q50: The first unit requires 10 hours to
Q51: There is a 30 percent chance that
Q52: Samuel, a project manager, and Martha, his
Q54: Stefan, a project manager in a publishing
Q55: Pogmon Solutions, a computer manufacturer, is introducing
Q56: Rachel, a project manager, has undertaken a
Q57: Victoria, an artisan who produces handcrafted furniture,
Q58: Define top-down and bottom-up budgeting.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents