A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
Without regard to demand, what is the minimum possible cycle time (in seconds) for this situation?
A) 162
B) 72
C) 54
D) 30
E) 6
Correct Answer:
Verified
Q93: Which of the following is not an
Q94: A common goal in designing process layouts
Q95: The maximum allowable cycle time is computed
Q96: Which of these items would be most
Q97: A layout in which workstations are grouped
Q99: In the use of closeness ratings for
Q100: Which one of these drive a machine
Q101: A company needs to rebalance a product
Q102: A company needs to rebalance a product
Q103: A company needs to locate three departments
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents