The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line 8 hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a case of Mint Chocolate Chip Cookies.
For output to equal projected demand, what is the theoretical minimum number of workstations needed?
A) 6
B) 4.5
C) 3
D) 2.7
E) 2
Correct Answer:
Verified
Q100: Which one of these drive a machine
Q101: A company needs to rebalance a product
Q102: A company needs to rebalance a product
Q103: A company needs to locate three departments
Q104: A company needs to rebalance a product
Q106: A company needs to rebalance a product
Q107: A company is designing a product layout
Q108: QRS Corp. is designing a product layout
Q109: A company is designing a product layout
Q110: The maker of the world-famous Chocolate Chip
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents