A local bagel shop produces two products: bagels (B) and croissants (C) . Each bagel requires 6 ounces of flour, 1 gram of yeast, and 2 tablespoons of sugar. A croissant requires 3 ounces of flour, 1 gram of yeast, and 4 tablespoons of sugar. The company has 6,600 ounces of flour, 1,400 grams of yeast, and 4,800 tablespoons of sugar available for today's production run. Bagel profits are 20 cents each, and croissant profits are 30 cents each.
For the production combination of 600 bagels and 800 croissants, which resource is slack (not fully used) ?
A) flour (only)
B) sugar (only)
C) flour and yeast
D) flour and sugar
E) yeast and sugar
Correct Answer:
Verified
Q57: In linear programming, sensitivity analysis is associated
Q58: The production planner for Fine Coffees, Inc.,
Q59: A redundant constraint is one that
A)is parallel
Q60: In linear programming, a nonzero reduced cost
Q61: The owner of Crackers, Inc., produces two
Q63: The owner of Crackers, Inc., produces two
Q64: A local bagel shop produces two products:
Q65: An electronics firm produces two models of
Q66: The production planner for a private label
Q67: An electronics firm produces two models of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents