Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is
A) 11.
B) 14.
C) 21.
D) 24.
E) 25.
Correct Answer:
Verified
Q48: Consider the portion of a project depicted
Q49: A hierarchical listing of what must be
Q50: Once a project is underway, the project
Q51: Which of the following is not true
Q52: Shortening activity durations is called
A)expediting.
B)crashing.
C)vendor management.
D)null nodes.
E)trade-off
Q54: A sequence of activities that leads from
Q55: To _ an activity means to shorten
Q56: Suppose a project is subject to the
Q57: Which of the following would probably not
Q58: Which of the following is not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents