Question 19

Multiple Choice

Which of the following is NOT necessary in order to recognise revenue under the percentage of completion method?


A) Total costs for the project are reasonably determinable.
B) The contract price (total revenue) must be reasonably certain.
C) There must be a reasonable assurance of payment.
D) Engineering estimates of the percentage of completion have been made.