Highrise Constructions Ltd had a large three-year project with total revenue of $5 000 000 and estimated total costs of $4 200 000.The project was 25 per cent complete at the end of the first year,55 per cent complete at the end of the second year and 100 per cent complete at the end of the third year.Revenues and costs were as estimated.
- How much profit was earned during the third year if the completion of production method was used?
A) $360 000
B) $440 000
C) $800 000
D) $400 000
Correct Answer:
Verified
Q5: On 1 January 2015,Romulus Ltd signed a
Q6: Revenue recognition means that:
A) revenue is not
Q7: Multi-Storey Builders Ltd had a large three-year
Q8: Which of the following statements about the
Q9: Revenue should be recognised when:
Q11: Multi-Storey Builders Ltd had a large three-year
Q12: Which of the following transactions should not
Q13: Highrise Constructions Ltd had a large three-year
Q14: Highrise Constructions Ltd had a large three-year
Q15: The most common critical event in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents