On 1 January 2017, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows: Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2017, 75 per cent complete at the end of 2018 and 100 per cent complete at the end of 2019. Revenues and costs were as estimated. How much profit was earned during 2019 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $14 000 000
D) None of the above
Correct Answer:
Verified
Q2: Revenue from a credit sale should not
Q3: Revenue should be recognised when:
Q4: Opec Ltd manufactures crystal balls. Transactions for
Q5: With respect to services provided, it is
Q6: The percentage of completion profit for a
Q8: Junction Company had the following transactions, among
Q9: The profit for a particular project of
Q10: Highrise Constructions Ltd had a large three-year
Q11: Under which of the following circumstances would
Q12: At what point would you expect revenue
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents