If it became clear that a project could not fulfil its purpose and meet the business case originally put forward, who would be responsible for cancelling the project?
A) The project sponsor
B) The project manager
C) The project board
D) The project team
E) The project leader
Correct Answer:
Verified
Q15: Which of the following statements is true
Q16: Once a proposal for approval is approved
Q17: A project's deliverables are:
A) the resources needed
Q18: When stakeholders ask for adjustments to a
Q19: The loss of support for a project
Q21: Capitalising on a risk to a project
Q22: Convening a 'lessons learned' meeting with team
Q23: When an activity that is part of
Q24: Team members working on a project will
Q25: During a project's execution phase, what percentage