Which of the following statements describes the difference between capacity requirements planning and material requirements planning?
A) Material requirements planning ignores capacity constraints.
B) Capacity requirements planning accounts for material.
C) Material requirements planning is confined by capacity constraints.
D) Capacity requirements planning only accounts for critical resources.
Correct Answer:
Verified
Q81: Which of the following plans generally includes
Q82: Which of the following measures should a
Q83: Which of the following is an input
Q84: At which of the following levels does
Q85: Material requirements planning provides recommendations for which
Q87: When determining a make or buy decision,
Q88: Which of the following circumstances will cause
Q89: Backward scheduling begins with which of the
Q90: Effective inventory management should lead to which
Q91: In which of the following environments is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents