A work center has 2 machines that are operated 16 hours a day for 5 days a week. Historically, the utilization has been 85% and the efficiency 105%. What is the rated capacity for this work center? (Rounded)
A) 71
B) 99
C) 130
D) 143
Correct Answer:
Verified