Question 522

Multiple Choice

An organization would like to bid on a project, but they don't have enough employees available to complete the work. The organization approaches a competitor with the opportunity to partner on the project to win the work. What type of risk response is used in this instance?


A) Sharing
B) Mitigation
C) Enhancing
D) Transference