A New Manager Received Computations of the Internal Rate of Return

Question 129

Multiple Choice

A new manager received computations of the internal rate of return regarding his project proposal. What should the manager compare the computation results to in order to determine whether the project is potentially acceptable?


A) Compare to the annual cost of capital.
B) Compare to the annual interest rate.
C) Compare to the required rate of return
D) Compare to the net present value.