The Table Below Provides Information About Tasks to Be Completed

Question 69

Essay

The table below provides information about tasks to be completed on a project,the precedence relationship between tasks and the expected times required to complete each task.Using this information,represent the project tasks on a Activity-on-Node (AON)network diagram,identify all the paths and the critical path,the critical tasks,the ES,EF,LS and LF times for each task and the time estimate for completing the project.
 Task  Estimated  completion  time (weeks)  Preceeding  tasks A2 None B3 A C2 AD4 BE3CF5D,EG3 F\begin{array} { | l | l | l | } \hline \text { Task } & \begin{array} { l } \text { Estimated } \\\text { completion } \\\text { time (weeks) }\end{array} & \begin{array} { l } \text { Preceeding } \\\text { tasks }\end{array} \\\hline \mathrm { A } & 2 & \text { None } \\\hline \mathrm { B } & 3 & \text { A } \\\hline \mathrm { C } & 2 & \mathrm {~A} \\\hline \mathrm { D } & 4 & \mathrm {~B} \\\hline \mathrm { E } & 3 & \mathrm { C } \\\hline \mathrm { F } & 5 & \mathrm { D } , \mathrm { E } \\\hline \mathrm { G } & 3 & \mathrm {~F} \\\hline\end{array}

Correct Answer:

verifed

Verified

The AON network diagram is depicted belo...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents