A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional insurance. Which of the following risk responses has occurred?
A) Avoiding
B) Mitigating
C) Accepting
D) Transferring
Correct Answer:
Verified
Q347: Which of the following is the BEST
Q348: Which of the following includes setting governance
Q349: Language barriers will MOST likely influence a
Q350: Which of the following charts would indicate
Q351: Which of the following methods should a
Q353: An engineer is troubleshooting a malfunctioning physical
Q354: The quarterly financial statement has been released,
Q355: A busy project manager has a diverse
Q356: A project manager is starting a project
Q357: Many questions have arisen regarding a newly
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents