Potters Limited uses a standard costing system for all its products. Potters Limited produces hand painted teapots. The standard direct labour time to paint one teapot is 1½ hours and the standard cost of labour is £20 per direct labour hour. Budgeted production is 1,500 teapots per month with budgeted monthly labour hours of 2,250. In October, Potters Limited produced 1,480 teapots and incurred total labour costs for painting the teapots of £43,659, paying £19.80 per hour for labour. What is the direct labour efficiency variance for October?
A) £300 Favourable
B) £441 Favourable
C) £600 Favourable
D) £741 Favourable
Correct Answer:
Verified
Q20: What is the correct formula for the
Q21: Maria runs a bakery, baking and selling
Q22: ABC Limited uses a standard costing system
Q23: QRS Limited uses a standard costing system
Q24: XDT Limited uses a standard costing system
Q26: QRS Limited uses a standard costing system
Q27: ZDT Limited uses a standard costing system
Q28: The Pottery Limited uses a standard costing
Q29: Which one of the following presents the
Q30: Which one of the following presents the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents