Which of the following is not one of the network rules for PERT/CPM?
A) Networks start and finish at multiple events.
B) Identify each unique activity within a project by a capital letter that corresponds only to that activity.
C) Branch direction indicates the general progression in time from left to right.
D) When a number of activities end at one event, no activity starting at that event may begin before all activities ending at that event are complete.
E) Two or more activities cannot share graphically the same beginning and ending events.
Correct Answer:
Verified
Q14: Because a project usually has a defined
Q17: Activities on the critical path in a
Q18: Learning-curve analysis highlights a key reason why
Q18: When a process crosses functional boundaries, there
Q20: The longest path (in time) through a
Q32: The primary objective of value analysis is
Q33: Organizations should not use process mapping to
Q54: Which of the following is not one
Q56: A _ visually displays the tasks and
Q60: A/An _ is a series of tasks
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents