In Williams V Roffey, Completing the Agreed Works on Time

Question 24

Multiple Choice

In Williams v Roffey, completing the agreed works on time and avoiding a contractual penalty clause was referred as what, so as to be good consideration?


A) An obviative intervention
B) A disbenefit mitigation
C) A practical benefit
D) A practical disbenefit

Correct Answer: