Solved

About Project Schedules, Which One Is True

Question 4

Multiple Choice

About project schedules, which one is true:


A) "events" represent a moment in time, such as the start or finish of something.
B) "activities" or "tasks" represent the actual doing of work and the passage of time.
C) both a and b
D) neither a nor b

Correct Answer:

verifed