With Smaller Batches (Circle All That Apply)

Question 12

Multiple Choice

With smaller batches (Circle all that apply)


A) The project finishes sooner since stages of the project overlap.
B) Quality decreases because defects are discovered later.
C) Earlier stages of the project can get feedback from later stages.
D) Work variability across departments in the project tends to increase.
E) Motivation increases because task deadlines are sooner.