In detailed survey of a hill road, the interval for plotting the contours at sharp curves is generally
A) 1 m
B) 2 m
C) 4 m
D) 6 m
Correct Answer:
Verified
Q15: Traffic engineering deals with the
A)traffic operation
B)design and
Q16: The main disadvantage of concrete roads is
Q17: For design purposes, average daily traffic should
Q18: The main advantage of providing super-elevation is
A)to
Q19: The universally recognized factor which affects the
Q20: A track of width 1 to 1.2
Q22: The grand trunk (G.T.) road was constructed
Q23: The transverse contraction joints in unreinforced concrete
Q24: The transverse joint may be a
A)expansion joint
B)contraction
Q25: The Indian Roads Congress (I.R.C.) was set