Typically,the ________ would be the most useful tools for scheduling,monitoring,and controlling the timing of a bridge construction.
A) ABC/EOQ models
B) CAD/CAE approaches
C) PERT/CPM techniques
D) TQM and CPI programs
Correct Answer: