Use the Information Below to Answer the Following Question(s)

Question 11

Multiple Choice

Use the information below to answer the following question(s) .
The following data for a pottery company pertain to the production of 2,000 clay pots during July.
Direct Materials (all materials purchased were used) :
Standard cost: $6.00 per kilogram of clay
Total actual cost: $11,200
Standard cost allowed for units produced was $12,000
Materials efficiency variance was $240 unfavourable
Direct Manufacturing Labour:
Standard cost is 2 pots per hour at $24.00 per hour
Actual cost per hour was $24.50
Actual labour was 972 hours
-What is the standard direct material amount per pot?


A) 1.00 kilogram
B) 1.88 kilograms
C) 2.12 kilograms
D) 3.00 kilograms
E) 4.00 kilograms

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents